Forward Tee Box Renovations (Holes 5, 6, 7, 8)

Renovations to four forward tee boxes were completed as part of the fall 2024 project. The work began with the Lake Panorama Association maintenance team removing railroad tie retaining walls on holes five, six, and seven. BluGrade Earthworks was hired to complete the remaining work.

A rainy fall slowed progress, but all dirt work was finished by the end of November. The forward tee boxes on holes five and seven were doubled in size. The teeing area on hole six remained roughly the same, with additional dirt added to the east side where the ground slopes away. The teeing area on hole eight was leveled.

Low-mow bluegrass sod was installed on hole seven, marking the completion of that tee box. However, wet field conditions and freezing temperatures prevented sod installation on the remaining three tees in fall 2024. Sod was laid on those tee boxes in early April 2025, and they were ready for play by early May.